Plans put solar panels at Detrick - Fort Detrick is striving to cut its demand on the energy grid by as much as 30 percent using renewable solar power within the next 18 months.

Large solar arrays cost somewhere around $3,400 per KW peak output.  So, a 15MW system is going to cost roughly $51mn.  Assuming Ft. Detrick has a natural gas supply, it could install a 15MW CHP system that would supply power and waste heat for heating and cooling for about $20mn or slightly less.  The solar PV system will have a capacity factor of roughly 15% meaning is will supply the base with 19,710MWh per year of energy.  The 15MW CHP system would supply about 124,800MWh per year and 170,400MMBTU of waste heat for heating and cooling.

Dumb-de-dumb-dumb, dumb.

396 Views Comments 0 Comments Comments Add Comment Author BioAuthor Bio
ReportReport This Post as Foul/Inappropriate
 
Toolbox

Blog Editor
Search
Calendar
Recent CommentsRecent Comments
RSS
Energy Central
Power Network


Sponsored Content

Copyright © 1996-2013 by CyberTech, Inc. All rights reserved.
Energy Central ® is a registered trademark of CyberTech, Incorporated.
CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central.
2821 S. Parker Rd. Ste 1105 Aurora, CO 80014
Contact: Phone - 303-782-5510 Fax - 303-782-5331 or service@energycentral.com.